
Technical Guidance Note 39
![]()
![]()
TOPIC: Testing to EN 61000-4-5
ISSUE: 4
REVISION DATE:
PREVIOUS REVISION DATE:
The present
version of this standard (1995) has raised issues which the EMCTLA working
group C believe require clarification or revision. These vary from aspects of application of the
surge to safety issues which have been brought to the attention of the working
group. The purpose of this TGN is to
provide guidance to members with the aim of achieving a more consistent
application of the standard.
Note. The IEC working group (SC77 WG11
now SC77B MT12) has a draft proposal of changes to the standard
(IEC61000-4-5:200X) which goes part way towards addressing some of the issues
discussed below. Where relevant these are reflected in the
recommendations. For instance, the
working group considered the issue of decreasing the number of pulses applied
but concluded that there was no technical justification for doing so.
An earlier
issue of TGN 39 went some way towards clarifying the application issue but
there are still found to be differences between testers in both method and
procedure. This issue of the TGN also
deals with other, wider aspects of the standard of concern to EMCTLA members.
The basic
standard should deal with the default procedure and test method. There will always be exceptions and special
cases and it may not be possible to encompass them all within the standard
whilst still preserving clarity. Thus
Product Committees may require specific test regimes involving differing phase
angles, maximum test levels, timing, and so on.
For other cases the product test plan can define the test set up and any
special parameters of the testing carried out.
The important point to keep in mind is the need to achieve repeatability
wherever possible.
(section 8.2 of the
Standard)
This reflects
the EMCTLA interpretation of the standard.
It does not conflict with anything written in the standard. It also reflects the most common
interpretation of the standard.
Test Levels: All lower severity levels shall be
tested up to the maximum specified by the product committee or test plan. The levels are 0.5kV, 1kV, 2kV, 4kV and x
(special).
Note.
The standard requires the test procedure to consider the non-linear I-V
characteristics of the EUT and states that for testing the secondary protection,
the output voltage shall be increased up to the let-through level of the
primary protection. For products specified to 0.5kV maximum a lower level of
250V may be used to test protection let-through. However, for compliance
testing, see the first bullet point under "Additional Application Considerations " of this TGN.
Phase Angle: For AC power ports (input or
output) the surges shall be applied synchronized to the AC voltage phase at 0°
or 180°, 90° and 270°.
Note
1: Product committees may select different phase angles as appropriate to the
product.
Note
2: While testing at both 0° and 180° is allowed, testing at only one zero
crossing point is considered to be required.
Note
3: For internally powered equipment and
sub-systems without the option of a.c or
Number of
Pulses/Polarity:
The product shall be tested with at least 5 positive and 5 negative surge
pulses at each test point, at each of the chosen phase angles and required
levels.
Time Between Pulses:
It is appreciated that the concerns over the test time and possible
component stress are not fully addressed in this TGN. These are matters which need consideration at
international level and may be the subject of a request for new work initiated
by the
The following flowchart represents the intended test sequence for the
application of surges. Exceptions would
be noted in the test plan or test report with reasons for departure.

·
When applying tests for CE marking the maximum level of surge
to be applied should be that given in the product specific or generic
standard. Applying additional
investigative tests or examining immunity up to the primary protection level
should be part of the manufacturer’s design proving work.
·
When applying surges in line-to-line mode to 3-phase AC
ports, testing is restricted to the combination, 3C2
(e.g. L1-L2, L1-L3, L2-L3, but NOT L1-L2 and
L2-L1, etc.). This is justified since both
polarities are tested on the lines under test.
·
Test operators should be aware of a possible safety hazard
when applying surges to shielded cables in accordance with clause 7.5 (figures 13 and 14 of the standard). In the event of a faulty shield connection a
dangerous charge may build up on the EUT (shown as EUT1 in the figures). To ensure the safety of the operator it may
be necessary to allow discharge of the cabinet between pulses.
Note. This can be achieved by the connection of 2x470kW HIGH VOLTAGE rated resistors connected to the chassis of
EUT1 (similar to the ESD coupling plane discharge network). Since the surge generator is not designed
for continuous operation and considering the maximum rate of application to be
1 pulse per 20 secs the resistors can safely be rated at 0.5W each. It is unlikely that the high value of
resistance introduced between chassis and ground will have a detrimental effect
upon the waveform of the generator.

Modified Figure 13 (figure 14 similarly modified)
·
The value R* in the test generator output is uncertain from
the standard (0W, 10W or 40W). Annex B.1 definitions appear to conflict with
the wording in clause 7.5. It is
recommended that until the IEC working group is consulted that R* be 0W (i.e no additional resistor) leaving the output impedance of
the generator as 2W (as given in clause 7.5).
·
Clause 7.5 (shielded lines) does not clarify where on the
shield the surge is to be applied. Where
a hand held probe exists (e.g. as supplied by Haefely) this can be applied to
the metalwork of the cabinet, but this may limit the repeatibility. Suggested guidance is to simulate real world
conditions. Hence application at the
usual earthing point of the chassis where provided or to a metallic connector
shield may be the best way of achieving realistic conditions.
·
Figures 6 and 7 do not differentiate connections or
feedthrough of the mains. Test operators
should ensure that the decoupling network case is connected to PE as is shown
in figures 8 and 9.
The advice given above is
based upon engineering judgement, comments from sources within the EMCTLA and
from IEC SC77B working group 11 draft working document.